Office of Waste Reduction & Recycling

OWRR Design Guidelines

Site & Space Planning C&D Waste Management Access to Buildings During Construction Requirements by Phase Waste Reduction Home

Printable Version

OWRR Access During Construction

Access to Buildings During Construction
Maintaining Services Staging Plans Container Removal Campus Dumpster Use

Refer to UNC-Chapel Hill Design Guidelines Chapter III: Construction Staging Areas, Pedestrian and Vehicular Access,Traffic Control and Pedestrian and Bike Safety Plans and Chapter IV: Construction Design Guidelines for Working Within and/or Near Occupied Buildings.

In order to maintain services to buildings under construction and adjacent buildings, OWRR and its contractors must be able to access dumpsters and loading docks during all phases of construction and renovation.1  Contact Ray Lanier (919) 962-7175.

The questions and considerations given in this section are designed to ensure continued and efficient solid waste services to campus buildings.

These issues must be addressed and discussed with OWRR throughout the design process.

1The information on this page can be found in the UNC Design Guidelines, Chapter I. General Principles, Section F. Waste Management, C. Office of Waste Reduction and Recycling Services to Buildings During Construction.

 Facilities Home   |  Energy Services   |  Planning & Construction   |  Campus Services   |  UNC Home   |  Contact Us