Before CDs are prepared, the
design team and the Office of Waste Reduction and Recycling meet to
confirm
outdoor service area requirements and equipment to be used.
Include section 02475 with any relevant site or space
planning requirements for this project.
Include section 11170 listing
requirements,
installation information, and suppliers for solid waste handling
equipment to be purchased BY the project—at a minimum, this will
include compactors.
Detailed plan sheets showing outdoor service area enclosures,
including:
screen wall details
electrical requirements
lighting
drainage
a list of buildings that the site(s) are intended to serve
An FINAL summary sheet listing all the outdoor service area
equipment to be used. This will include:
the type of equipment (example: 8 yd. cardboard dumpster),
the estimated cost,
whether the project, FP&C or the customer is purchasing them, and
the locations (if there’s more than one building in the project).
BeforeCDs are prepared, the design team and the Office of Waste
Reduction and Recycling meet to confirm indoor recycling locations and
any special situations.
Include section 02475 with any relevant site or
space planning requirements for this project.
Include Section 12300 Manufactured Casework listing
requirements for recycling cabinets
Clearly marked locations of all indoor recycling locations
-AND- detail sheets showing the plans for any recycling cabinets
to be built by the project
An FINAL summary sheet listing all the indoor recycling sites. This will include the:
indoor recycling locations,
which locations will use cabinets,
whether the project, FP&C or the customer is purchasing them, and
the amount reserved for cabinets that are not being built by the project.
Before CDs are prepared, the design team and the Office of Waste
Reduction and Recycling meet to confirm walkway recycling locations and
any special situations.
Include Section 02870 listing the walkway recycling containers to be
used and their placement.
Clearly marked plans showing the locations of all walkway recycling locations.
An FINAL summary sheet
listing all the walkway recycling sites. This will include the:
walkway recycling locations,
whether the project or FP&C is purchasing them, and
the amount
reserved for walkway bins (assuming that FP&C will be purchasing
them).
CD staging plans and site drawings
should include plans for access to the building (if
occupied) and adjacent buildings such that deliveries and recycling/waste collection services can be maintained.
CD demo plans shall note the requirement of contacting the Office of Waste Reduction
and Recycling to remove indoor and outdoor containers (including
dumpsters) as the project phasing affects different areas.
Based on Valuable & Reusable Building Material Inventory
Reuse in project based on inventory:
Discussion and FINAL decisions by design team and construction manager at risk.
Create a plan for storage of materials.
CD submittal requirement:
Decisions are to be integrated into specs and drawings: 01505,
02070, and appropriate infomation and drawings.
Reuse in other projects:
Design team and construction manager at risk circulate
FINALlist to Facilities Planning and other design teams.
Create a plan for transfer and storage of
items.
CD submittal requirement:
Salvage to be listed in 01505, 02070 and appropriate section and drawings.
Outside salvage/recycle:
FINAL list
Market research by design team
and construction manager at
risk, with assistance from Office of Waste Reduction and
Recycling
CD submittal requirement: Any potential
recyclables are to be listed in 01505 as a FINAL list of
required and
suggested materials. Any salvage is to be listed in 02070 and
appropriate section and drawings.
At CD phase, FINAL plan for building materials and non-moveable FFE:
Storage for reuse in Project
Transfer for reuse on campus
Delivery to Owner (Surplus and Shops)
The information on this page can be found in the UNC Design Guidelines,
Chapter II. Project Development Process, B. Project Development Sequence, d)
Construction Document Phase, (1) Construction Document Design Submittal, (a) A
sheet of drawings containing…, (g) These requirements related to recycling and
waste management…, and (5) Final Movable Fixture, Furniture, & Equipment (FFE)
Inventory.