OWRR Requirements by Phase: Design Development
Requirements by Phase
Schematic Design Design Development Construction Documents
Pre-Bid Pre-Construction Construction Project Close-Out
Click here for this file as a word document. Project Completion
Outdoor Service Area

Order all recycling/solid waste equipment for the project.  The final list should have been part of the CD phase. 

Arrange for installation of the recycling/solid waste equipment per drawings and requirements in the Construction Documents.

Coordinate installations with the Office of Waste Reduction and Recycling.

Office of Waste Reduction and Recycling provides any equipment not purchased as part of the project, labels equipment, coordinates a collection schedule with staff and contractors, and provides billing information to the accounting department.

Indoor
Walkway

Access

Resume normal access to buildings.

Building Material Assessment and Salvage

Provide the Office of Waste Reduction and Recycling with a summary of ACTUAL recycling, reuse and salvage activities for the project.  This is to include, but is not limited to:
  • quantities landfilled, recycled, reused, and salvaged;
  • a break down of the types of materials recycled, reused and salvaged; the percent of total waste of each of the categories listed; 
  • the destinations of these materials;
  • the economic impact of these activities on the project; and any success stories or challenges incurred.

Fixtures, Furniture and Equipment Assessment and Salvage

The information on this page supplements the UNC Design Guidelines, Chapter II. Project Development Process, B. Project Development Sequence, f) Construction Phase, (4) Project Close-Out Responsibilities.