OWRR Requirements by Phase: Schematic
Requirements by Phase
Schematic Design Design Development Construction Documents
Pre-Bid Pre-Construction Construction Project Close-Out
Click here for this file as a word document. Schematic Design (SD)
Outdoor Service Area List existing recycling and dumpster locations on the existing condition site plans.

Indoor
Amy Preble provides feedback about where recycling locations need to be and gives an overview of indoor recycling requirements.
Walkway Ray Lanier and Sarah Myers provide feedback about locations.

Access

List other buildings that utilize the dumpster and recycling sites shown on existing condition site plans.

Building Material Assessment and Salvage

Building Material Walkthrough

Initial walkthrough by the design team TO DETERMINE what valuable and reusable materials are available for:

  • Reuse in this project,
  • Reuse in other campus projects,
  • Reuse by the general public,
  • Recycled (required and suggested).
  • SD submittal requirement: Valuable & Reusable Building Material Inventory [Initial list at this time]

Fixtures, Furniture and Equipment Assessment and Salvage

Designers and customers begin thinking about what will and will not be reused in the finished project and during temporary housing.

The information on this page can be found in the UNC Design Guidelines, Chapter II. Project Development Process, B. Project Development Sequence, b) Schematic, (1) Existing Site Conditions and (4 ) Schematic Design Submittal. 