Refer to UNC-Chapel Hill Design Guidelines Chapter III: Construction Staging Areas, Pedestrian and Vehicular Access,Traffic Control and Pedestrian and Bike Safety Plans and Chapter IV: Construction Design Guidelines for Working Within and/or Near Occupied Buildings.

In order to maintain services to buildings under construction and adjacent buildings, OWRR and its contractors must be able to access dumpsters and loading docks during all phases of construction and renovation.  Contact Ray Lanier (919) 962-7175.

The questions and considerations given in this section are designed to ensure continued and efficient solid waste services to campus buildings.

These issues must be addressed and discussed with OWRR throughout the design process.

Staging Plans

Existing Conditions:

The existing condition drawings must show the current location of all dumpsters and carts that will be impacted by construction, fencing or traffic pattern shifts.

During Construction:

Phasing, staging, and site limit plans must show the temporary location and traffic patterns (vehicular and pedestrian) for all dumpsters and carts temporarily relocated as a result of the project.

All non-essential containers or those to be moved (and the new location), must be denoted on the plans as such.  See Container Removal below.